ICE Launches Tool to Predict Data Center Construction Delays
Intercontinental Exchange has launched a tool that helps developers, lenders, investors and municipalities assess the risk of a data center project being delayed or halted before they commit capital. The ICE Data Center Site Analytics Tool covers more than 3,100 U.S. counties and combines permit records with local utility costs and economic data.
ICE trained its construction disruption model on thousands of U.S. permitting and project outcomes. The company said the model achieved 77% accuracy when tested against historical permit outcomes. That figure describes how the model performed in past testing; the tool produces a separate estimate of the probability that an individual project will face disruption within 24 months.
“Data center capital is moving faster than local permitting and community consensus, and that gap is now a material financial risk,” said Larry Lawrence, head of ICE’s geospatial intelligence team. He said a 12-month delay on a median-sized $2.7 billion project can cost $162 million to $270 million.
The tool tracks thousands of existing U.S. data centers across 47 layers of geographic data. It examines county permitting trends, past delays and stoppages, project values and fees. At the site level, it considers electricity and water costs alongside local indicators such as broadband access and unemployment. ICE also uses its U.S. Mortgage Rate Lock Index at the time a permit is filed as an indicator of market conditions.
The tool is part of ICE’s geospatial intelligence business, which tracks more than 100 million U.S. properties and more than 50,000 municipal bond issuers.